Office of Computing Services
Laptop/Projector Project for Secondary
Schools
March 21, 2006
INTRODUCTION
On Monday,
March 20, 2006, the Greenwood School District 50 Board of Trustees approved a
plan for distributing laptop computers to teachers at both
high schools, two middle schools, the career center, and the alternative
school. The plan also includes the
distribution of computer projectors to each regular classroom at each of those
six sites. The distribution of the technology
(laptops and projectors) is contingent upon the completion of three hours of
staff development for each teacher receiving the equipment.
SCOPE OF PROJECT
The
following table includes the counts of teachers (from personnel files for each
school) to receive laptops, the counts of regular classrooms (from school floor
plans) in which projectors will be placed, and the number of staff development
groups (with a maximum of 20-22 participants) to be scheduled at each site:
|
Site |
Number of Laptops |
Number of Projectors |
Number of Staff Dev Groups |
|
GHS |
93 |
75 |
5 |
|
EMD |
50 |
49 |
3 |
|
NSD |
47 |
29 |
3 |
|
WST |
44 |
31 |
3 |
|
SSD |
12 |
8 |
1 |
|
VOC |
20 |
12 |
1 |
|
Totals |
266 |
206 |
13 |
Note: Teachers at all nine elementary schools and
IMPLEMENTATION SCHEDULE
The
following tentative implementation schedule has been proposed for the secondary
laptop/projector project:
By Wednesday, March 22, 2006 Quotes due from vendors of laptops and
projectors
By Wednesday, April 5, 2006 Delivery of laptops and projectors to
district warehouse
By Friday, April 7, 2006 OCS inventory laptops and
projectors; label boxes for school delivery; install image and configure
computers
By Monday, April 17, 2006 Laptops and projectors delivered
to schools; at GHS and EMD, laptops for Staff Development Group 1 inventoried
in Follett and distributed to those teachers
Tuesday, April 18, 2006 Staff development begins at
EMD and GHS for Group 1’s (3:45 – 5:15 pm or 3:45 – 6:45 (group decision))
By Wednesday, April 19, 2006 All laptops at
all the above sites inventoried in Follett, configured for designated users,
and distributed to teachers; projectors distributed to designated classrooms
Wednesday, April 19, 2006 Continue staff development
activities based on schedule below
By Monday, May 8, 2006 All
staff development completed, as scheduled, with all teachers at the schools
listed above completing a minimum of three hours of hands-on activities
STAFF DEVELOPMENT SCHEDULE
|
April 18
& April 19: 3:45 – 5:15
|
April 27
& May 1: 3:45 – 5:15
|
May
4: 3:30 – 6:30
|
|
April 20
& April 24: 3:45 – 5:15
|
May 2: 3:30 – 6:30
|
May
8: Times TBA
|
|
April 25
& April 26: 3:45 – 5:15
|
May
3: 3:30 – 6:30
|
|
Note: Groups at GHS and EMD may opt for one-day
sessions from 3:45 to 6:45 if all members of the group agree. In those cases, adjustments may be made in
other group schedules to fill slots made available by the changes.