(boldfaced items are complete)


Project Status Update:  Elementary Schools

 1/17/06  Board approved plan for elementary schools
 1/20/06  Laptop computers and projectors ordered
 1/30/06  Projectors delivered to district
 1/31/06  Projectors delivered to schools

 2/3/06  Laptops delivered to district
 2/3/06 – 2/4/06  OCS staff configure laptops in preparation for delivery to schools

 2/6/06  Laptops delivered to elementary media centers

 2/6/06 – 2/10/06  Barcode labels and record entry into Follett (in school libraries); delivery of accessories (laptop bags, flash drives, network cables, mice, speakers)

 2/13/06 – 2/14/06  Anticipated distribution of laptops to teachers
 2/21/06 – 4/6/06  Staff development for every elementary school teacher
            Completed:  OAK, PIN, LAK, END, SPR, MAT, HOD, MER, WFD

           

Project Status Update:  Middle and High Schools

 1/17/06  Board approved plan for middle and high schools

 1/31/06  OCS staff and staff from NSD, EHS, GHS meet to plan labs

 1/31/06  Computers ordered for NSD, EHS, GHS labs

 2/6/06 Projectors provided for each new lab at NSD, EHS, and GHS

 2/7/06 – 2/10/06  Laptop training for BRW teachers

 2/10/06  Anticipated delivery date for computers (to district)

 2/13/06 – 2/20/06  Setup computers and delivery to schools

 2/21/06 – 3/3/06  Cabling, switches, furniture, and other tasks for preparing labs

 

Project Status Update:  Secondary Schools

 3/20/06  Board approved plan for secondary schools
 3/21/06  Laptop computers and projectors ordered
 4/5/06  Laptops to be delivered to district
 4/6/06 – 4/7/06  OCS staff configure laptops in preparation for delivery to schools

 4/17/06  Projectors delivered to district
 4/17/06  Laptops delivered to secondary media centers

 4/17/06 – 4/19/06  Barcode labels and record entry into Follett (in school libraries); delivery of accessories (laptop bags, flash drives, network cables, mice, speakers)

 4/17/06 – 4/21/06  Anticipated distribution of laptops to teachers
 4/18/06  Projectors delivered to schools

 4/18/06 – 5/8/06  Staff development for every secondary school teacher
            Completed:  BRW, NSD, WST, EMD, GHS, VOC, SSD, Make-up #1

            Week of 5/8/06:  Middle and high school administrators

            Week of 5/15/06:  Make-up session #2

 

 

 

Revised 5/9/06